CompTIA Project+ (PK0-004) — Question 382
A cost baseline is used to measure the:
Answer options
- A. eventual cost of a project.
- B. increase in the budget.
- C. variance with the initial budget.
- D. inevitable cost overruns.
Correct answer: A
Explanation
The cost baseline serves as a reference point for measuring the total expected cost of a project, making option A correct. Options B, C, and D are incorrect because they refer to budget increases, variances, and overruns rather than the baseline itself.