CompTIA Project+ (PK0-004) — Question 381
A project manager has requested the procurement department collect detailed solutions with cost estimates from qualified third-party vendors.
This is an example of an:
Answer options
- A. MOA
- B. RFP
- C. RFI
- D. RFQ
- E. MOU
Correct answer: D
Explanation
The correct answer is D, RFQ (Request for Quotation), as it specifically involves soliciting detailed pricing from vendors. The other options, such as RFP (Request for Proposal) and RFI (Request for Information), do not primarily focus on cost estimates, while MOA (Memorandum of Agreement) and MOU (Memorandum of Understanding) are not procurement documents.