CompTIA Project+ (PK0-004) — Question 373

A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. Which of the following BEST describes how the project manager can keep the project on track?

Answer options

Correct answer: B

Explanation

Option B is correct because rearranging the installation dates allows the project to utilize available resources effectively and avoid further delays. Options A, C, and D do not address the fundamental issue of the delayed device and may lead to additional complications or costs without resolving the scheduling conflict.