CompTIA Project+ (PK0-004) — Question 372
A project manager notices that project status meetings have been going awry. The project manager decides to limit the meetings to only those participants who have input. Which of the following should the project manager use to communicate to stakeholders who will no longer attend the meetings but need to be kept informed?
Answer options
- A. Communication plan
- B. Status report
- C. Action items
- D. Meeting minutes
Correct answer: D
Explanation
The correct answer is D, as meeting minutes provide a detailed record of what was discussed and any decisions made during the meeting, which is essential for keeping absent stakeholders informed. Options A, B, and C do not specifically detail the outcomes of the meetings and may not provide the same level of context as meeting minutes.