CompTIA Project+ (PK0-004) — Question 358

A critical project team member has fallen ill and must take leave for two weeks. The project manager recognizes this will affect the product release, but the sponsor mandates the product must go live on the date marketing published. Which of the following is the BEST response?

Answer options

Correct answer: D

Explanation

The correct answer is D because reducing the features and delivering iterative updates allows the team to meet the release deadline while ensuring quality. Options A, B, and C do not address the underlying issue of resource availability and may compromise the project's overall success and quality.