The stakeholders for an active project requested a change that could potentially increase the projected budget. Which of the following should the project manager do NEXT?

Answer options

Correct answer: B

Explanation

The correct response is to update the risk register and notify the risk owners because a change request that may increase the budget introduces new risks that need to be managed. Updating the requirements document, incident response plan, or issue log does not directly address the potential risks associated with the budget change.