The stakeholders for an active project requested a change that could potentially increase the projected budget. Which of the following should the project manager do NEXT?
Answer options
- A. Update the requirements document and notify the project team.
- B. Update the risk register and notify the risk owners.
- C. Update the incident response plan and notify the project sponsor.
- D. Update the issue log and discuss it with the stakeholders.
Correct answer: B
Explanation
The correct response is to update the risk register and notify the risk owners because a change request that may increase the budget introduces new risks that need to be managed. Updating the requirements document, incident response plan, or issue log does not directly address the potential risks associated with the budget change.