CompTIA Project+ (PK0-004) — Question 357
A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organization and would mark a significant change in approach from previous projects. Which of the following should the project manager contact for guidance and approval for the new methodology?
Answer options
- A. Project coordinator
- B. Project team
- C. Project management office
- D. Project sponsor
Correct answer: C
Explanation
The Project Management Office (PMO) is responsible for setting standards and methodologies across projects, making them the ideal contact for guidance on adopting a new iterative approach. While the project team, project sponsor, and project coordinator may provide input or support, they do not typically oversee methodology changes at the organizational level.