CompTIA Project+ (PK0-004) — Question 344

After a change request is approved, a vendor shares the estimated delivery date with project management. A key stakeholder requests to have this change completed by an earlier date. Which of the following is the BEST action for the project manager to take?

Answer options

Correct answer: A

Explanation

The best action for the project manager is to negotiate with the vendor to see if an earlier completion of the change is feasible, addressing the stakeholder's concern directly. Evaluating the impact of switching tasks (B) is important but does not address the request directly. Consulting with the CCB (C) may delay the process, and confronting the stakeholder (D) is unproductive and could harm relationships.