CompTIA Project+ (PK0-004) — Question 344
After a change request is approved, a vendor shares the estimated delivery date with project management. A key stakeholder requests to have this change completed by an earlier date. Which of the following is the BEST action for the project manager to take?
Answer options
- A. Negotiate with the vendor to complete the change earlier.
- B. Evaluate the impact of switching tasks on the schedule.
- C. Consult with the CCB about the request.
- D. Confront the stakeholder about the unrealistic request.
Correct answer: A
Explanation
The best action for the project manager is to negotiate with the vendor to see if an earlier completion of the change is feasible, addressing the stakeholder's concern directly. Evaluating the impact of switching tasks (B) is important but does not address the request directly. Consulting with the CCB (C) may delay the process, and confronting the stakeholder (D) is unproductive and could harm relationships.