CompTIA Project+ (PK0-004) — Question 343
The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?
Answer options
- A. Network diagram
- B. Product backlog
- C. Program
- D. Portfolio
Correct answer: B
Explanation
The correct answer is B, as a Product backlog organizes tasks that are interrelated and depend on similar processes. The other options do not specifically refer to a collection of tasks or functions aimed at achieving a business goal within a framework that allows for shared operational processes.