CompTIA Project+ (PK0-004) — Question 345

Which of the following project management roles is responsible for estimating the duration of tasks?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the project team collectively estimates task durations based on their expertise and input. While the project manager (C) oversees the project, they rely on the team's estimates rather than providing them directly. The project scheduler (A) organizes the timeline but does not create the estimates, and the project coordinator (D) assists in communication and logistics, not estimation.