CompTIA Project+ (PK0-004) — Question 337

A project team has identified project risks. Which of the following is the NEXT step?

Answer options

Correct answer: A

Explanation

The next logical step after identifying project risks is to prioritize them, which allows the team to focus on the most critical risks first. Planning, communicating, and reviewing can occur afterward, but prioritization is essential to determine which risks require immediate attention.