CompTIA Project+ (PK0-004) — Question 336

A project team just updated several risk response strategies in the risk management plan. Which of the following documents should be updated NEXT?

Answer options

Correct answer: A

Explanation

The management plan needs to be updated next because it provides a comprehensive overview of how the project will be managed, including updates to risk responses. The other documents, such as the scope statement, issue log, and communication plan, do not directly relate to the adjustments made in the risk management plan.