CompTIA Project+ (PK0-004) — Question 335
A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced during the first planning workshop?
Answer options
- A. Gantt chart
- B. RACI
- C. WBS
- D. Risk register
Correct answer: C
Explanation
The Work Breakdown Structure (WBS) is typically developed in the first planning workshop to outline the project's deliverables and tasks. While a Gantt chart, RACI, and risk register are important, they are created after defining the WBS to aid in scheduling, assigning responsibilities, and identifying risks.