CompTIA Project+ (PK0-004) — Question 338
A project in development has excessive power requirements. In response, the company is going to use solar and wind power. Which of the following risk strategies is being utilized?
Answer options
- A. Exploiting
- B. Accepting
- C. Mitigating
- D. Transferring
Correct answer: C
Explanation
The correct answer is C, Mitigating, because the company is taking proactive steps to reduce the excessive power requirements by utilizing renewable energy sources. Options A (Exploiting) and D (Transferring) do not apply here as they involve different approaches to managing risks, while B (Accepting) would imply acknowledging the risk without taking action.