CompTIA Project+ (PK0-004) — Question 338

A project in development has excessive power requirements. In response, the company is going to use solar and wind power. Which of the following risk strategies is being utilized?

Answer options

Correct answer: C

Explanation

The correct answer is C, Mitigating, because the company is taking proactive steps to reduce the excessive power requirements by utilizing renewable energy sources. Options A (Exploiting) and D (Transferring) do not apply here as they involve different approaches to managing risks, while B (Accepting) would imply acknowledging the risk without taking action.