CompTIA Project+ (PK0-004) — Question 332
A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)
Answer options
- A. Quality because the existing system is now outside the threshold.
- B. Requirements because this is a change to initial scope.
- C. Cost because replacing the system incurs additional expense.
- D. Schedule because this was an unscheduled task and will impact the timeline.
- E. Stakeholders because they will need to understand the modification and provide buy-in.
Correct answer: C, D
Explanation
The correct answers are C and D because replacing the system will incur additional costs, making cost a significant constraint affected by the change. Additionally, since the modification was not planned, it will disrupt the project timeline, impacting the schedule constraint as well. Options A, B, and E, while relevant, do not directly relate to the immediate changes stemming from the decision to house a different reptile.