The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?

Answer options

Correct answer: C

Explanation

The correct answer is C because developing a mitigation plan is essential to address the potential impact of the storm on the project. Options A and B do not focus on creating a proactive strategy to manage the risk, while option D suggests rescheduling without a structured approach to mitigate the risk.