CompTIA Project+ (PK0-004) — Question 333
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?
Answer options
- A. Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
- B. Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
- C. Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
- D. Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
Correct answer: C
Explanation
The correct answer is C because developing a mitigation plan is essential to address the potential impact of the storm on the project. Options A and B do not focus on creating a proactive strategy to manage the risk, while option D suggests rescheduling without a structured approach to mitigate the risk.