CompTIA Project+ (PK0-004) — Question 331
A project manager launched a survey for future end users of a new product under development. The sponsor received the survey results and realized the needs are different than the features currently being developed. The sponsor decided to cancel the project. Which of the following explains why the sponsor made this decision?
Answer options
- A. Constraint reprioritization needed to be carried out.
- B. The cost of the changes would be more than planned.
- C. The survey was not stated in the project management plan.
- D. More than half of the project charter should be updated.
Correct answer: A
Explanation
The correct answer is A because the sponsor recognized that the initial constraints, such as user needs, needed to be reassessed based on the survey results. Options B and C do not accurately reflect the situation since the decision was based on differing needs rather than cost or planning omissions. Option D is also incorrect as it does not directly relate to the primary reason for canceling the project.