CompTIA Project+ (PK0-004) — Question 317

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?

Answer options

Correct answer: A

Explanation

The correct answer is A, Exploitation, as it involves taking advantage of opportunities that can improve project outcomes. The other options—Avoidance, Acceptance, and Mitigation—focus on dealing with threats or risks rather than leveraging opportunities for success.