CompTIA Project+ (PK0-004) — Question 318

A project team has just finished one phase of product development and is gathering requirements for the next phase. Which of the following methodologies is being applied?

Answer options

Correct answer: A

Explanation

The Waterfall methodology is characterized by its sequential phases, where each phase must be completed before moving on to the next. In this case, the team is gathering requirements after finishing one phase, which aligns with the Waterfall approach. The other methodologies like Agile and PRINCE2 focus more on iterative processes and flexibility, which do not fit the described scenario.