CompTIA Project+ (PK0-004) — Question 316
A project manager asks a project coordinator to put together a milestone report to present to the board of directors showing how the project has progressed in the last three months.
The coordinator shares a 45-page document detailing all that has happened so far on the project.
Which of the following is MOST likely the issue?
Answer options
- A. The document is too lengthy and includes extraneous details
- B. The document follows the appropriate template for a communication plan
- C. The document contains data that is aggregated for an executive review.
- D. The documents clear regarding the objectives and status, including graphs.
Correct answer: A
Explanation
The correct answer is A because a 45-page document is likely too detailed for a milestone report intended for the board, which typically requires concise information. Options B, C, and D suggest that the document is appropriate, but they do not address the core issue of length and relevance, making them incorrect.