CompTIA Project+ (PK0-004) — Question 313
A project must be:
Answer options
- A. continuous.
- B. budgeted.
- C. unique.
- D. complex.
Correct answer: C
Explanation
The correct answer is C, as a project is defined by its uniqueness, meaning it is a one-time endeavor with specific objectives. Options A and D may describe aspects of some projects, but they do not apply universally to all projects. Option B is important but does not define the essence of a project.