CompTIA Project+ (PK0-004) — Question 314
During the planning phase, a scheduler uses a WBS as a reference to create a list of activities. The next step of the process is to provide a sequence for all the activities. With which of the following deliverables is the scheduler working?
Answer options
- A. WBS dictionary
- B. Project timeline
- C. Network diagram
- D. Gantt chart
Correct answer: B
Explanation
The correct answer is B, the Project timeline, as it outlines the sequence of activities over a specific time period. The WBS dictionary (A) provides detailed information about the WBS elements but does not establish a sequence. A Network diagram (C) visualizes the relationships and dependencies between tasks but is not a timeline itself, while a Gantt chart (D) displays tasks over time but does not inherently provide the sequencing of activities.