CompTIA Project+ (PK0-004) — Question 312

Which of the following risk management activities identifies the severity of a risk event?

Answer options

Correct answer: A

Explanation

Quantification is the process that measures the impact or severity of a risk event, making it essential for prioritizing risks. Identification focuses on recognizing risks, while Response and Mitigation pertain to planning and implementing actions to address risks, not assessing their severity.