CompTIA Project+ (PK0-004) — Question 312
Which of the following risk management activities identifies the severity of a risk event?
Answer options
- A. Quantification
- B. Identification
- C. Response
- D. Mitigation
Correct answer: A
Explanation
Quantification is the process that measures the impact or severity of a risk event, making it essential for prioritizing risks. Identification focuses on recognizing risks, while Response and Mitigation pertain to planning and implementing actions to address risks, not assessing their severity.