CompTIA Project+ (PK0-004) — Question 307

Joe, a team member, is dissatisfied with his assigned project tasks, and he communicates this to his manager. His manager arranges a meeting with the project manager. Together, they decide Joe needs additional training to be able to execute the assigned project tasks. Which of the following is the company's organizational structure?

Answer options

Correct answer: C

Explanation

The correct answer is C, Matrix, as it reflects a structure where employees report to multiple managers, allowing for collaborative decision-making and shared responsibilities. The other options, like Projectized, Vertical, and Functional, suggest more rigid structures where tasks and authority are less flexible and collaborative.