CompTIA Project+ (PK0-004) — Question 306
Which of the following is an attribute of a potential project?
Answer options
- A. Makes no changes to the work environment
- B. Has no authoritative body
- C. Comprises ongoing operational activities
- D. Can be completed in one hour
Correct answer: D
Explanation
The correct answer is D because a project is often defined by its temporary nature, and having a clear end point like one hour aligns with this definition. Option A is incorrect because projects can change the work environment, option B is wrong as projects typically have some form of authority, and option C is misleading since ongoing activities are part of operations, not projects.