CompTIA Project+ (PK0-004) — Question 308
To maintain an active project's progress, the project manager does not acknowledge any opposing input that was provided. Which of the following techniques is this an example of?
Answer options
- A. Mitigating
- B. Negotiating
- C. Forcing
- D. Avoiding
- E. Accepting
Correct answer: D
Explanation
The correct answer is D, Avoiding, because it refers to the act of not addressing or acknowledging opposing viewpoints to keep the project on track. The other options like Mitigating, Negotiating, and Forcing involve some level of engagement or confrontation with the opposing input, which the project manager in this scenario is not doing. Accepting does not apply as it implies acknowledgment rather than dismissal.