CompTIA Project+ (PK0-004) — Question 300

Which of the following indicators will assist the project manager in determining the health of the budget?

Answer options

Correct answer: B

Explanation

CPI, or Cost Performance Index, is a key indicator used to evaluate the cost efficiency and financial health of a project. While SV (Schedule Variance), AC (Actual Cost), EV (Earned Value), and ETC (Estimate to Complete) are important metrics as well, they do not specifically provide insight into budget efficiency like CPI does.