CompTIA Project+ (PK0-004) — Question 299
Which of the following documents will MOST likely result in a time and material agreement?
Answer options
- A. RFQ
- B. RFI
- C. SLA
- D. RFB
Correct answer: C
Explanation
A Service Level Agreement (SLA) typically outlines the expected service performance and can lead to time and materials agreements as it defines the scope of work and performance metrics. In contrast, an RFQ (Request for Quotation) and RFI (Request for Information) are primarily used for gathering information and pricing, while an RFB (Request for Bid) is usually associated with fixed-price contracts.