CompTIA Project+ (PK0-004) — Question 301

A project manager is receiving too many emails and telephone calls from the project team concerning project issues. To minimize the emails and calls, the project manager created a shared weekly status report template on the intranet and instructed the project team to use it. Which of the following should the team members include in the weekly report? (Choose three.)

Answer options

Correct answer: A, B, C

Explanation

The correct options are A, B, and C because task completion dates provide a timeline for progress, meeting minutes summarize discussions and decisions, and issues highlight problems needing attention. Options D, E, F, and G, while relevant to project management, do not directly contribute to the weekly status update focused on current project challenges.