CompTIA Project+ (PK0-004) — Question 286
Which of the following documents will MOST likely result in a time and material agreement?
Answer options
- A. RFQ
- B. RFI
- C. SLA
- D. RFB
Correct answer: D
Explanation
An RFB (Request for Bid) is typically used to solicit bids for projects where costs can vary based on time and materials used, making it the most likely to result in a time and material agreement. In contrast, RFQ (Request for Quotation) and RFI (Request for Information) are more focused on gathering specific pricing or information rather than establishing contract terms, while SLA (Service Level Agreement) defines performance metrics rather than cost structure.