CompTIA Project+ (PK0-004) — Question 287

Which of the following project phases would include a feasibility study?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the initiating phase is where a feasibility study is conducted to assess whether the project is viable. The planning phase focuses on defining the project scope and objectives, while monitoring and controlling is about tracking progress, and executing is about performing the work defined in the project management plan.