CompTIA Project+ (PK0-004) — Question 285
When a project milestone is completed, which of the following activities ensures the quality of the deliverables at that point in the project?
Answer options
- A. Gate review
- B. Lessons learned
- C. Audit
- D. Baseline review
Correct answer: A
Explanation
The correct answer is A, Gate review, as it is specifically designed to assess the quality and readiness of deliverables at predefined stages in a project. The other options, while they contribute to project success, do not focus on the immediate quality assessment of deliverables at the milestone completion.