When a project milestone is completed, which of the following activities ensures the quality of the deliverables at that point in the project?

Answer options

Correct answer: A

Explanation

The correct answer is A, Gate review, as it is specifically designed to assess the quality and readiness of deliverables at predefined stages in a project. The other options, while they contribute to project success, do not focus on the immediate quality assessment of deliverables at the milestone completion.