CompTIA Project+ (PK0-004) — Question 284

A project manager has been experiencing resistance from a group of stakeholders.
With which of the following should the project manager consult to reduce friction going forward?

Answer options

Correct answer: C

Explanation

The project sponsor is typically the individual who has the authority to make decisions and provide support for the project, which can help reduce stakeholder resistance. The other options, while important, do not have the same level of influence or responsibility in addressing stakeholder concerns.