CompTIA Project+ (PK0-004) — Question 279

A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks. Which of the following documents should the project manager create LAST?

Answer options

Correct answer: C

Explanation

The MOU (Memorandum of Understanding) is typically created last because it outlines the agreement and understanding between parties after the requirements and specifics have been established through other documents like the RFI, NDA, and RFQ. The other options serve different purposes in the vendor selection and engagement process, making them necessary prior to finalizing the MOU.