CompTIA Project+ (PK0-004) — Question 278
A project sponsor wants to know which tasks are next in the project but is unable to find this information. Which of the following may need to be adjusted?
Answer options
- A. Scope document
- B. Status report
- C. Issue log
- D. Risk log
Correct answer: B
Explanation
The correct answer is B, as the status report is designed to provide updates on project progress, including upcoming tasks. If the status report lacks this information, it may need to be revised. The other options, such as the scope document, issue log, and risk log, do not primarily focus on the immediate tasks and their scheduling.