CompTIA Project+ (PK0-004) — Question 280

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

Answer options

Correct answer: D

Explanation

Estimating the work package is the logical next step after all tasks have been identified and grouped. This estimation helps in understanding the time and resources needed for each work package. The other options involve subsequent steps that require prior estimation to effectively allocate resources, define quality standards, or identify task interdependencies.