CompTIA Project+ (PK0-004) — Question 270

A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule.
Which of the following would the project manager most likely do NEXT?

Answer options

Correct answer: A

Explanation

The correct answer is A, as creating a Work Breakdown Structure (WBS) is essential for organizing project activities and serves as the foundation for further planning. Options B, C, and D are important steps but typically follow the creation of the WBS, which outlines the project's scope and tasks.