CompTIA Project+ (PK0-004) — Question 270
A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule.
Which of the following would the project manager most likely do NEXT?
Answer options
- A. Create a WBS.
- B. Determine predecessors and dependencies.
- C. Determine the critical path.
- D. Prioritize tasks.
Correct answer: A
Explanation
The correct answer is A, as creating a Work Breakdown Structure (WBS) is essential for organizing project activities and serves as the foundation for further planning. Options B, C, and D are important steps but typically follow the creation of the WBS, which outlines the project's scope and tasks.