A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.)

Answer options

Correct answer: C, E

Explanation

Options C and E are correct because they ensure the vendor receives a physically signed purchase order quickly. Option A is slower as mailing can take time, and Option B does not meet the vendor's requirement for a physical signature. Option D also fails to provide a physical signature directly to the vendor.