CompTIA Project+ (PK0-004) — Question 269
A manager is reviewing some projects with two project managers who are working on the financial system.
Which of the following BEST describes this type of review?
Answer options
- A. Operations
- B. Project
- C. Portfolio
- D. Program
Correct answer: D
Explanation
The correct answer is D, Program, as it refers to a group of related projects managed in a coordinated manner to obtain benefits and control not available from managing them individually. Options A (Operations) and B (Project) do not encompass multiple projects, while C (Portfolio) refers to a collection of projects and programs but not necessarily a review of projects in progress.