CompTIA Project+ (PK0-004) — Question 268

A project manager is collecting work package information from the project team for the first time.
Which of the following elements should the project manager have at the end of the meeting?

Answer options

Correct answer: A

Explanation

The correct answer is A because task name, duration, and dependencies are essential components that define the work packages. Options B, C, and D include elements that may be relevant later in project planning but are not the primary information required at the initial collection stage.