CompTIA Project+ (PK0-004) — Question 258

A project team is brainstorming and documenting what might go wrong in a project, the possible impact, and potential actions should certain situations arise.
Which of the following contains actions the team is MOST likely to consider?

Answer options

Correct answer: A

Explanation

The correct answer is A because identifying risks, collaborating on solutions, and quantifying impacts are essential steps in effective risk management. Options B, C, and D mention actions related to risk response but do not encapsulate the brainstorming and documentation process as comprehensively as option A does.