CompTIA Project+ (PK0-004) — Question 259
A project manager for a projectized organization is notified that a team member is ill and will be out for an extend period of time. This team member is the only person with a key skill set.
Which of the following should the project manager notify FIRST regarding the team member's absence?
Answer options
- A. Project sponsor
- B. Human resources office
- C. Budget office
- D. Project team
Correct answer: B
Explanation
The project manager should notify the Human resources office first because they are responsible for handling employee-related issues, including absences. While informing the project sponsor, budget office, or project team may also be necessary, addressing the absence with HR is the immediate priority for managing the situation effectively.