CompTIA Project+ (PK0-004) — Question 256
A project is moving into the next phase, and those involved with planning will not actually perform the work.
After the project team members have been identified and assigned to do the work, which of the following has changed?
Answer options
- A. Project
- B. Schedule
- C. Baseline
- D. Stakeholder
Correct answer: D
Explanation
The correct answer is D, as the stakeholders involved in the project may change when the project moves to a new phase and different individuals are engaged for the execution. The project itself, schedule, and baseline remain constant in this context, as they do not inherently change with the assignment of team members.