CompTIA Project+ (PK0-004) — Question 25

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.
Which of the following documents should the project coordinator use?

Answer options

Correct answer: A

Explanation

The correct answer is A, the Risk register, as it is specifically designed to track potential risks and their management strategies. The Issue log is used for tracking problems that have occurred, the Communication plan outlines how communications will be handled, and the Status report provides updates on project progress rather than focusing on risks.