CompTIA Project+ (PK0-004) — Question 24
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
Answer options
- A. Cost, schedule, organizational chart, and risks/issues
- B. Risks/issues, cost, RACI chart, and action items
- C. Schedule, cost, risks/issues, and milestones
- D. Action items, organizational chart, schedule, and NDA
Correct answer: C
Explanation
The correct answer, C, includes schedule, cost, risks/issues, and milestones, which are essential for quickly understanding the project's status. Options A and B include less relevant information such as organizational charts and RACI charts, which do not provide immediate insight into project progress. Option D lists action items and an NDA, which are not critical for assessing the project's status.