CompTIA Project+ (PK0-004) — Question 26

A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the situation illustrates a cultural practice where employees are allowed to take naps at certain times, which the project manager did not consider. Options A and B are not relevant here because the issue is not about communication or time differences, and D is too broad since it pertains to individual choices rather than cultural norms.