CompTIA Project+ (PK0-004) — Question 228
Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
Answer options
- A. Email and instant messaging to project team members and the project team members and the project sponsor
- B. Text messages to and voice conferences with all stakeholders and project team members
- C. Video conferences with key stakeholders and the project champion
- D. Instant messaging to the project coordinator and project scheduler
Correct answer: A
Explanation
Option A is correct because email and instant messaging are effective for quick updates among project team members and the project sponsor during a business continuity incident. The other options either involve broader audiences that might not need immediate updates (B) or less effective communication methods for urgent information (C and D).