CompTIA Project+ (PK0-004) — Question 227
A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?
Answer options
- A. Crashing the schedule
- B. Prioritizing tasks
- C. Determining milestones
- D. Developing sprints
Correct answer: B
Explanation
The project manager is prioritizing tasks by deciding to include an unscheduled deliverable in the next phase to meet stakeholder expectations. Crashing the schedule refers to speeding up the project timeline, which is not the case here. Determining milestones pertains to setting key dates, while developing sprints is relevant to Agile methodologies, not the current scenario.