CompTIA Project+ (PK0-004) — Question 226
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Answer options
- A. Dashboard
- B. Communication plan
- C. Statement of work
- D. Project charter
Correct answer: A
Explanation
The correct answer is A, Dashboard, as it provides a visual representation of key metrics and progress, making it ideal for high-level reporting. The other options, while important documents, do not serve the primary purpose of summarizing information for stakeholders in a concise manner.