CompTIA Project+ (PK0-004) — Question 225

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?

Answer options

Correct answer: B

Explanation

The correct answer is B, as scope creep refers to the uncontrolled expansion of project scope without adjustments to time, cost, and resources. Allowing changes during the delivery phase can lead to scope creep, which project managers seek to avoid. The other options, while relevant to project management, do not directly address the issue of making changes to the project scope at this stage.